Now Payra To Cut Down Power Production By Half

2024-11-13 15:50

Wedoany.com Report-Nov 13,  Amid the backdrop of all other coal-based power plants in the country, including India's Adani, the production of a unit of Payra Thermal Power Plant went into maintenance today.

The only full-phased coal-based plant will available at half of its 1,320 megawatts (MW) capacity for the next two months, according to the plant authorities.

For all latest news, follow The Daily Star's Google News channel.

They said, a 660MW unit of Payra Thermal Power Plant suspended production from 12:00am today.

With the new update, the power production with coal fired power plants dropped below 2,000MW, which was more than 3,000MW last week. The country's capacity to produce from coal plants is 7,099MW.

Manager of the plant Shah Abdul Mawla told The Daily Star that the production of the second unit of the Payra plant went into major maintenance which will take two months at least.

Once after the maintenance is completed, the full production might delay for another 20-25 days as another unit will require a regular maintenance then, he said.

The superintending engineer of this power plant Zobayer Ahmed said it is a scheduled maintenance which was delayed twice earlier considering the power demand of the country.

"But we got the clearance now," he said, adding that as winter started, power demand dropped.

Contacted, deputy assistant engineer of Patuakhali Power Grid Abdullah Al Naeem said they will not be facing any trouble in Patuakhali as power demand dropped at 45MW from 108MW for the last couple of days.

Currently, Bangladesh has been producing between 11,000MW to 12,000MW electricity, having around 500MW shortage during peak hours.

This newsletter is compiled and reprinted from the global Internet and strategic partner information, and it is only for readers' communication. If there are any infringements or other issues, please inform us timely, this site will be modified or deleted. Email: news@wedoany.com
Bulletin
Tasmanians To Benefit From $122m Hydro Dividend PowerChina Achieves Power Generation Target 51 Days Ahead Of Schedule Reclamation And Partners Complete Negotiations For The B.f. Sisk Dam Raise And Reservoir Expansion Project, Advancing Water Supply Reliability In California’s Central Valley Reclamation, DWR Celebrate Launch Of Key Delta Habitat Restoration Project Agencies Seek Comment On Draft Programmatic Environmental Assessment Addressing Federal Support Of The Phase 2 Implementation Plan: Testing The Feasibility Of Reintroducing Salmon In The Upper Columbia River Basin Bangladesh, India, Nepal, Bhutan should think of creating a South Asian grid: Prof Yunus IWT Creating Hurdles In J&k Potential Hydel Power Generation: Cm Omar Transforming Hydropower with the Power of Digital Twins in Dam Operations Consultant Sought To Study Strengthening Of The Andekaleka Hydropower Dam In Madagascar Bringing Clarity to the Just in Just Coal Transition Pumping the Brakes on Coal Plant Retirements Hydraulic To Pneumatic: A Solution To Effective Ash Conveying And Utilisation Cop: Adb, Kazakhstan Tie Up On Early Coal Retirement Southern CEO: Data Center Demand, Regulatory Changes Could Keep Coal-Fired Units Online ČEz Secures Uranium Supply Contract Birchwood Park: A Nuclear Hub Evolution IAEA Conducts Disused Sealed Radioactive Sources Technical Centre Peer Review Mission in Slovenia IAEA and EBRD Expand Cooperation to Nuclear Energy to Help Reach Net Zero Nuclear Provides Jobs Boost To Bristol, Says EDF Energy Tsuruga 2 Non-compliant With Safety Standards, Regulator Rules