Wedoany.com Report-Nov 18, Vestas has won two orders in Germany for a total of 194MW.
The first is with MIBRA for 15 V162-6.2MW turbines for the 93MW Breunsdorf in Sachsen project.
Delivery is due to begin in second quarter 2026 with commissioning scheduled for first quarter 2027.
The second order is from Windpark Reinhardswald for 18 V150-6.0MW machines in 5.6MW operating mode.
Delivery to the 101MW Windpark Reinhardswald in Hessen project begins in second quarter 2025 with commissioning scheduled for fourth quarter 2026.