BNSF Completes Phase Two of Cicero Intermodal Expansion Project

2024-11-14 11:45

Wedoany.com Report-Nov 14, The completion of phase two brings several infrastructure improvements designed to increase capacity and efficiency at the Cicero facility.

BNSF Railway has reached a milestone in its multi-year Cicero Intermodal Expansion Project in Illinois.

Key developments in this phase include:

Addition of a new production track extending 4,530 feet, improving operational capacity.

Reconstruction of 43,000 feet of receiving yard track for an optimized layout.

Construction of a new trailer parking lot providing over 470 parking stalls.

Establishment of a new hostler repair shop.

Installation of a new 100-foot diameter turntable.

In alignment with sustainability efforts, BNSF optimized site grading to reduce excavation, recycled existing pavement, and repurposed excess soil on an adjacent site. These measures contributed to a reduction of 5,971 metric tons in greenhouse gas emissions. Collaboration with the local municipality led to the design and construction of a stormwater detention system that improves stormwater runoff control in the community.

The entire expansion project is expected to be completed by 2026, aiming to increase production capacity to meet current demand and accommodate future growth.

This newsletter is compiled and reprinted from the global Internet and strategic partner information, and it is only for readers' communication. If there are any infringements or other issues, please inform us timely, this site will be modified or deleted. Email: news@wedoany.com
Bulletin
Tasmanians To Benefit From $122m Hydro Dividend PowerChina Achieves Power Generation Target 51 Days Ahead Of Schedule Reclamation And Partners Complete Negotiations For The B.f. Sisk Dam Raise And Reservoir Expansion Project, Advancing Water Supply Reliability In California’s Central Valley Reclamation, DWR Celebrate Launch Of Key Delta Habitat Restoration Project Agencies Seek Comment On Draft Programmatic Environmental Assessment Addressing Federal Support Of The Phase 2 Implementation Plan: Testing The Feasibility Of Reintroducing Salmon In The Upper Columbia River Basin Bangladesh, India, Nepal, Bhutan should think of creating a South Asian grid: Prof Yunus IWT Creating Hurdles In J&k Potential Hydel Power Generation: Cm Omar Transforming Hydropower with the Power of Digital Twins in Dam Operations Consultant Sought To Study Strengthening Of The Andekaleka Hydropower Dam In Madagascar Bringing Clarity to the Just in Just Coal Transition Pumping the Brakes on Coal Plant Retirements Hydraulic To Pneumatic: A Solution To Effective Ash Conveying And Utilisation Cop: Adb, Kazakhstan Tie Up On Early Coal Retirement Southern CEO: Data Center Demand, Regulatory Changes Could Keep Coal-Fired Units Online ČEz Secures Uranium Supply Contract Birchwood Park: A Nuclear Hub Evolution IAEA Conducts Disused Sealed Radioactive Sources Technical Centre Peer Review Mission in Slovenia IAEA and EBRD Expand Cooperation to Nuclear Energy to Help Reach Net Zero Nuclear Provides Jobs Boost To Bristol, Says EDF Energy Tsuruga 2 Non-compliant With Safety Standards, Regulator Rules